{pgfgantt} concerns making Gantt charts based on the pgf package.

provides the possibility to produce Gantt charts (see figure) with LaTeX and the pgf package. A Gantt chart is a graphical representation of a project structure with a horizontal time axis and the time span of different project parts showing as bars. The Gantt chart can also shows couplings between project parts as well as important events.

The pgfgantt package is available on CTAN

Gantt chart produceed with pgfgantt Image from Wikipedia Commons. Gantt chart produced with pgfgantt

281 questions
14
votes
3 answers

pgfgantt - Milestones with different styles

Can I have two sets of milestones in one gantt chart? Each with a different style (such as colour, shape, etc.)?
val
  • 143
12
votes
1 answer

pgfgantt: Is it possible to create bars with "double" labels?

here's a problem I have: I want my gantt bars to have two types of labels -- one on the side of the chart, and one inline -- and I'm having a hard time making it work. The code I use to generate the chart is listed below:…
8
votes
1 answer

Getting gantt chart week to show week number

I am using ganttchart to make a time plan for my master thesis but when I set the calendar week text to \currentweek it does not "reset" on new year but just keeps going. The fist week number is correct but in January I have week 54 instead of…
Kajsa
  • 677
8
votes
1 answer

Descriptive label for gantttitle

I'm using pgfgantt within MikTeX (both latest version) running fine. In my gantt diagramm I have three title-lines: First year, than month and beneath the project month. I'd like to place the text project month in the last title line just aligned…
8
votes
1 answer

How to draw a monthly gantt chart with quarterly vgrid?

I recently updated my pgfgantt package, and can't figure out how to update one of my charts to draw properly under the new package. The chart has a two-tiered title, years over months. It also had a quarterly vertical grid. It's the quarterly…
mac
  • 311
7
votes
2 answers

Expand a Gantt chart automatically to textwidth of a page

I want nearly every Gantt-Chart to fit automatically to the textwidth of a page. The big word in that question is automatic. And that is what it differs from other questions like that. The textwidth and the count of timeslots in the chart are not…
buhtz
  • 1,180
7
votes
1 answer

pgfgantt: Named links in order to maintain relationship between bars

I have a pretty complex pgfgantt chart. Several people are collaboratively working on it and it is subject to frequent change. In this chart the individual \ganttbar items are linked with the \ganttlink command. The ganttbar items are referred to by…
6
votes
1 answer

How do I add a legend to a gantt chart?

I'm using the pgfgantt package to draw a gantt chart and I am using different fill patterns for different task types (fill patterns for the task bars, that is). It works nicely! But I would like to add a legend to tell the reader which pattern…
Christoph
  • 2,467
6
votes
1 answer

PGFGantt Compressed Calendar by week?

I'd like to use \gantttitlecalendar to generate a title with week as the smallest unit (i.e. one unit = one week). By default, each unit represents one calendar day: \begin{ganttchart}[ hgrid, vgrid, time slot format=isodate, …
6
votes
1 answer

How can I move an inline labels up in pgfgantt?

Let's look at one of the example Gantt charts from the documentation: \documentclass{standalone} \usepackage{pgfgantt} \begin{document} \begin{ganttchart}[vgrid, hgrid, inline]{12} \gantttitle{Title}{12} \\ \ganttbar{Task 1}{1}{3} \ganttbar[bar…
Grzenio
  • 9,465
5
votes
1 answer

pgfgantt: month displayed as single letter

I'd like my months to be listed as single letters (e.g. J, F, M, A, M, J, J...) What's the easiest way to do this? This MWE lists months as MM numbers: \documentclass[tikz]{standalone} \usepackage{pgfgantt} \begin{document} \begin{ganttchart}[ …
5
votes
1 answer

Automatic size for gantttitle

I have two questions with pgfgantt package: How to adjust automatically the size of the third row? (For example when it's written "Vacances de Paques and for "February") How to add the date (for example a label) next to the milestone ? Here is…
Warok
  • 743
5
votes
0 answers

Generating new type of GanttLink in ganttchart

Can I add new link types in ganttchart ? Because I wanna draw a process that starts when an other process sends to him the first input. In addition, processess report theirs ends to others. The image bellow describe the situation I want. I have…
4
votes
1 answer

How to remove the text after the calculate percentage in a pgfgantt?

I would like to remove the "complete" after the percentage in the progress label and keep the 60% only, without a digit. Thank you for your help. Please find bellow a…
4
votes
1 answer

How to create a Gant-Chart in LaTeX-Beamer

I am trying to create a Gant-Chart in Beamer. I found the following example: \documentclass{beamer} \usepackage[utf8]{inputenc} \usepackage{pgfgantt} \title{Sample…
Luk
  • 509