I am working on a file in MS Project. I have a task that is auto-scheduled and the duration is 365 days. The start date is 7/5 and the calculated finish date is 5/24 which is obviouslby not correct. I have my calendar set to 7 day working week. Thank you for any help!
Asked
Active
Viewed 829 times
1 Answers
0
Create a calendar based on the 24 hr calendar, with the following customisation:
Hours per day: 7.3
Hours per week: 51
Days per month: 100
Duration is entered in: Months
Default task type: Fixed Duration
jwamiza
- 1
Can you give us year as well as date data? Do you have resource's assigned with a different working time definition? In File > Options, Schedule - what is your definition of hours per day?
– JulieS Feb 23 '15 at 19:24