Microsoft Project Standard 2010 - set start time by clock not calendar

sI have a project that I need to run 24/7 with no breaks. I need to set task start times at specific times of day. How can I do that? IE. if task 1 takes 4 hours and task 2 takes 3 hours; how can I set task 1 to start at 6AM and task 2 at to start…
Harry
  • 41
  • 1
  • 1
  • 2
1
vote
1 answer

MS Project Diverse skilled resources

I have a project that has developers assigned to them. I know that some of my tasks are done in x time by developer A, but the same tasks would be done in 1.5 x time by developer B, because A is more experienced than B. Is there a way I can include…
1
vote
0 answers

How can I change settings on part of (divided) task?

I want to know how to split a task i several parts and how to change settings separately for each part (different color for instance). I have been working in another planning tool where this is possible. Is is possible with MS project?
1
vote
1 answer

Automate Microsoft Project 2010 launch

I am looking for some way for automate Microsoft Project 2010 launching when exported file is created by another project management software. Is it possible to force MSP2010 to open the file?
Fil
  • 11
0
votes
1 answer

MS Project - task is 365 days, but calendar dates are less

I am working on a file in MS Project. I have a task that is auto-scheduled and the duration is 365 days. The start date is 7/5 and the calculated finish date is 5/24 which is obviouslby not correct. I have my calendar set to 7 day working week.…
0
votes
1 answer

How can a show a task that has a window for completion

I have several tasks within a project that take 2 days but have a three month window in which to complete how do I show this on my gantt chart?
0
votes
1 answer

summary tasks in Microsoft project 2010

if i add a summary task in microsft project planning how do i make 3/4/5..... tasks below under it. i have created summary tasks but the tasks beneath them are not consistent. for example week 5(summary task) admin view prototype with flows final…
0
votes
1 answer

how can set email notifications for milestones in microsoft project 2010

Is there a way for setting automatic notifications for milestones in microsoft 2010? I would like to send a reminder email two days before a task ends.